City of Vancouver permit and SWCAA sequence
The City’s demolition permit page asks whether asbestos is present. If it is, you are sent to SWCAA for the Notice of Intent to Remove or Encapsulate Asbestos, and to L&I for certification and notification. The usual order of work looks like this:
- AHERA inspection of the building or the part being demolished.
- For buildings more than 50 years old, photos of each elevation for the DMO application.
- SWCAA Notice of Demolition with the inspection report, plus a Notice of Intent for any asbestos removal.
- The 10-day wait, counted from the day SWCAA has the complete notice and fees.
- Asbestos removal, with waste sealed, labeled and taken to the disposal site named on the notice.
- Demolition on the dates given in the notice.
Removing a septic system or a fuel tank near the foundation, or placing fill below natural grade, brings its own City requirements. The City’s permit page lists them.
The inspection standard is covered in asbestos testing and AHERA surveys. If siding or pipe insulation has asbestos, it comes out first. You can see the residential asbestos removal we do on the homepage.